Six Week Look ahead May 7, 2018

Week of May 7

·         Exterior Vapor Barrier and Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Build out of new Electric Room – Building A

·         Grounding and Transformer Pad for New Electric Service to Building A

·         Overhead & In Wall MEP, begin regular AHJ In Wall Inspections – All Floors -  West to East - Building A

·         Gypsum Board and Taping at 1st and 3rd Floors

·         Roof and Metal Panel for Bridge Pre-Assembly

·         Waterproof & Backfill for Building C Elevator Foundation

·         Pour concrete infills for Stair A – Building A

·         Start Steel Framing for Stair D – Building A

Week of May 14

·         Exterior Vapor Barrier and Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Start Windows – West to East – Building A

·         Build out of new Electric Room – Building A

·         UI – Pull Wire from Pole in Street to new Transformer for New Electric Service to Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – All Floors -  West to East - Building A

·         Gypsum Board and Taping at 1st and 3rd Floors

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Continue Steel Framing for Stair D – Building A

·         Rig Roof Top Equipment to Roof – Building A

·         Piping and Duct on Roof – Building A

·         Low Roof Over Cafeteria – Building A

Week of May 21

·         Exterior Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Windows – West to East – Building A

·         Start Metal Panel at East End – Building A

·         Complete AHJ In Wall Inspection – 3rd Floor East

·         Build out of new Electric Room – Secondary from Transformer to Switchgear – Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – 2nd Floor – West to East - Building A

·         Gypsum Board and Taping at 1st and 3rd Floors

·         Build out Mechanical Rooms on 1st Floor – Building A

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Complete Steel Framing for Stair D & Pour Concrete – Building A

·         Piping and Duct on Roof – Building A

·         Prime and 1st Coat Paint on 3rd Floor West – Building A

Week of May 28

·         Exterior Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Windows – West to East – Building A

·         Metal Panel at East End – Building A

·         Build out of new Electric Room – Secondary from Transformer to Switchgear – Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – 2nd Floor –  West to East - Building A

·         Gypsum Board and Taping at 1st and 3rd Floors

·         Build out Mechanical Rooms on 1st Floor – Building A

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Piping and Duct on Roof – Building A

·         Prime and 1st Coat Paint on 1st Floor East – Building A

·         Pull Low Voltage Wiring on 3rd Floor West

Week of June 4

·         Exterior Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Windows – West to East – Building A

·         Metal Panel at East End – Building A

·         Build out of new Electric Room – Secondary from Transformer to Switchgear – Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – 2nd Floor -  West to East - Building A

·         Gypsum Board and Taping at 1st , 2nd  and 3rd Floors

·         Build out Mechanical Rooms on 1st Floor – Building A

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Piping and Duct on Roof – Building A

·         Prime and 1st Coat Paint on 1st Floor West – Building A

·         Pull Low Voltage Wiring on 1st Floor East – Building A

·         Start Ceiling Grid on 3rd Floor West – Building A

·         Start Kitchen Ceilings – Building A

Week of June 11

·         Windows – West to East – Building A

·         Start up Permanent Power – Building A

·         Start Up Roof Top Equipment – Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – 2nd Floor -  West to East - Building A

·         Gypsum Board and Taping at 1st, 2nd and 3rd Floors

·         Build out Mechanical Rooms on 1st Floor – Building A

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Install Piping and Duct on Roof – Building A

·         Prime and 1st Coat Paint on 3rd Floor East – Building A

·         Pull Low Voltage Wiring on 1st Floor East – Building A

·         Start Ceiling Grid on 1st Floor East and continue on 3rd Floor west – Building A

·         Kitchen Ceilings – Building A