Week of March 19

·         Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

·         Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Roofing for Temp. Watertight – West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st Floor -  West to East - Building A

·         Bathroom Carriers – 1st Floor

·         Isolation Ceiling in Kitchen – Building A

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Delivery of Bridge for Prefab

Week of March 26

·         Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

·         Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Complete Roofing for Temp. Watertight – West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead MEP – 1st Floor/3rd Floor-  West to East - Building A

·         In Wall MEP Rough - 1st/2nd/3rd Floors -  West to East - Building A

·         Bathroom Carriers – 1st Floor/3rd Floor

·         Isolation Ceiling in Kitchen – Building A

·         Start AVB - 1st/2nd/3rd Floor - West to East - Building A

·         Fireproofing – 1st Floor – Building A

·         Rig Rooftop Equipment to Roof – Building A

·         Excavate for Elevator Pit – Building C

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Decking/Framing/Roofing

Week of April 2

·         Stair/Interior CMU Walls - 1st/2nd/3rd Floor - West to East - Building A (New Instructional Building)

·         Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st/2nd/3rd Floors -  West to East - Building A

·         Bathroom Carriers – 3rd Floor/2nd Floor

·         Isolation Ceiling in Kitchen – Building A

·         AVB - 1st/2nd/3rd Floor - West to East - Building A

·         Rig Rooftop Equipment to Roof – Building A

·         Install Rooftop MEP – Building A

·         Install Foundations for Elevator Pit – Building C

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Framing

Week of April 9

·         Stair/Interior CMU Walls – 1st/2nd/3rd Floor - West to East - Building A (New Instructional Building)

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st/2nd/3rd Floors -  West to East - Building A

·         AVB - 1st/2nd/3rd Floor - West to East - Building A

·         Install Rooftop MEP – Building A

·         CMU Walls for Elevator – Building C

·         Brick/Precast Installation - 1st/2nd/3rd Floor - West to East - Building A

·         Steel Pan Stairs – North/East - Building A

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Insulation/Sheathing/AVB/Metal Panel

·         Misc. Prep Work in Building C (Spring Break)

·         Run Sanitary Line on East Parcel (Spring Break)

Week of April 16

·         Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st/2nd/3rd Floors -  West to East - Building A

·         AVB - 1st/2nd/3rd Floor - West to East - Building A

·         CMU Walls for Elevator – Building C

·         Brick/Precast Installation - 1st/2nd/3rd Floor - West to East - Building A

·         Steel Pan Stairs – North/East - Building A

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Metal Panel

Week of April 23

·         Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st/2nd/3rd Floors -  West to East - Building A

·         AVB - 1st/2nd/3rd Floor - West to East - Building A

·         CMU Walls for Elevator – Building C

·         Brick/Precast Installation - 1st/2nd/3rd Floor - West to East - Building A

·         Steel Pan Stairs – North/East - Building A

·         Start Metal Panel – West Elevation – Building A

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Metal Panel