The Month Ahead at Stratford High School

I've you've been in the neighborhood over the past few months, you probably noticed the new building rising next to the High School.  The brand new, state of the art instructional building continues to be built at a rapid pace.  This is what is happening now, and planned for the next month, as the Project Team continues to bring Stratford High School into the 21st century.

Week of February 19

  • Exterior/Stair/Interior CMU Walls - 1st Floor/2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – West - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Water Tie In at King Street for Hydrant

  • Electric Room Infrastructure & Rough-in – Building A

  • Install new Gas Service from California Street for Building A

 

Week of February 26

  • Stair/Interior CMU Walls - 1st Floor/2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – West/North - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Water pipe from King Street curb line for Hydrant

  • Electric Room Infrastructure & Rough-in – Building A

  • Test Pit for Building C Elevator Foundations – East Parcel

  • Install new Gas Service from California Street for Building A

     

Week of March 5

  • Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – North - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Electric Room Infrastructure & Rough-in – Building A

  • Deliver Bridge Structure

 

 

Week of March 12

  • Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – North/East - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Electric Room Infrastructure & Rough-in – Building A

  • Prefab of Bridge – Decking/Framing/Roofing/Metal Panel

  • Start Ductwork – 1st/3rd Floors - West to East - Building A

     

     

Week of March 19

  • Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – North/East - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Electric Room Infrastructure & Rough-in – Building A

  • Prefab of Bridge – Decking/Framing/Roofing/Metal Panel

  • Install Ductwork – 1st/3rd Floors - West to East - Building A

  • Start Overhead MEP – 1st/3rd Floors -  West to East - Building A

     

     

Week of March 26

  • Start Exterior Wall AVB

  • Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – East/South - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Complete Roofing – West to East - Building A

  • Electric Room Infrastructure & Rough-in – Building A

  • Prefab of Bridge – Decking/Framing/Roofing/Metal Panel

  • Install Ductwork – 1st/3rd Floors - West to East - Building A

  • Overhead MEP – 1st/3rd Floors -  West to East - Building A