The Month Ahead at Stratford High School

Week of January 15

  • Decking/Detailing - Roof - West to East - Building A (New Instructional Building)

  • Prep/Pour of Slab on Decks - 2nd Floor - West to East - Building A

  • Exterior/Stair CMU Walls - 1st Floor - West to East - Building A

  • Storm Drainage South of the Detention Basin - West Parcel

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

 

Week of January 22

  • Decking/Detailing - Roof - West to East - Building A (New Instructional Building)

  • Prep/Pour of Slab on Decks - 2nd/3rd  Floor - West to East - Building A

  • Exterior/Stair/Interior CMU Walls - 1st Floor - West to East - Building A

  • Exterior Cold Formed Metal Framed Walls/Blocking/Densglas - 1st Floor - West to East - Building A

  • Storm Drainage South of the Detention Basin - West Parcel

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

     

Week of January 29

  • Complete Decking/Detailing - Roof - Building A (New Instructional Building)

  • Prep/Pour of Slab on Decks - 3rd Floor/Roof - West to East - Building A

  • Exterior/Stair/Interior CMU Walls - 1st Floor - West to East - Building A

  • Exterior CFMF Walls/Blocking/Densglas - 1st Floor - West to East - Building A

  • Steel Pan Stairs - West Stair - Building A

  • Interior Framed Wall Layout - 1st Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Sanitary Line South Side of Building A

     

Week of February 5

  • Complete Pour of Slab on Decks - 3rd Floor/Roof - West to East - Building A (New Instructional Building)

  • Exterior/Stair/Interior CMU Walls - 1st Floor - West to East - Building A

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs - West/North Stair - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Sanitary Line South Side of Building A

     

     

Week of February 12

  • Exterior/Stair/Interior CMU Walls - 1st Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd - West to East - Building A

  • Steel Pan Stairs – North Stair - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Sanitary Lateral from King Street Manhole Stub Out to Curb Line onto East Parcel

     

Week of February 19

  • Exterior/Stair/Interior CMU Walls - 1st Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – North - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Water Tie In at King Street for Hydrant