The Month Ahead at Stratford High School - September and October

Week of September 18

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Install Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Water Tie-In at King Street

  • Test Pit at King Street for Sanitary Manhole

Week of September 25

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Backfill Footings and Under-slab at Building A (New Instructional Building)

Week of October 2

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Removal of Contaminated Soil at Detention System

  • Backfill Footings and Under-slab at Building A (New Instructional Building)

Week of October 9

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Continue Removal of Contaminated Soil at Detention System

  • Backfilling Footings, Utilities and Under-slab at Building A (New Instructional Building)

Week of October 16

  • Start Prep of Slab Subgrade Building A (New Instructional Building) - West

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Backfilling Footings, Utilities and Under-slab at Building A (New Instructional Building)

Week of October 23

  • Continue Prep of Slab Subgrade Building A (New Instructional Building) - West

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Backfilling Footings, Utilities and Under-slab at Building A (New Instructional Building)

  • Pour Slab on Grade – West End – Building A (New Instructional Building)