The Month Ahead at Stratford High School - August and September 2017

Week of August 21

  • Prep Parking Lot at West Parcel (@ California Street)

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Install Storm Drainage at West Parcel

  • Restore Landscaping, Paving & Sidewalk at North and West of Existing Building C (East Parcel)

  • Form & Install Rebar for Stairs to Basement at North of Existing Building C (East Parcel)

  • Export Topsoil from 25 North Parade (Acquired Residential Property)

Week of August 28

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Pour Stairs to Basement at North of Existing Building C (East Parcel)

Week of September 4

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Start Storm Detention System at West Parcel

Week of September 11

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Continue Storm Detention System at West Parcel

  • Start Backfilling Footings at Building A

Week of September 18

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Continue Storm Detention System at West Parcel

  • Continue Backfilling Footings at Building A

  • Start Under-slab Utilities at Building A

  • King Street Water Line Tie-in for Existing Building C

Week of September 25

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Continue Backfilling Footings at Building A

  • Continue Under-slab Utilities at Building A