The Month Ahead at Stratford High School - July 18, 2017

 

Work is underway to make the new state of the art Stratford High School a reality.  See below for a summary of the activities that will be happening on the site over the next month.  All activities are subject to change due to weather conditions, etc. Regular updates will be posted here so check back frequently!

Week of July 17:

  • Remove topsoil and install Turner Construction field office on the West Parcel
  • Begin demolition of the Field House
  • Install the Turner Construction field office at 25 North Parade
  • Fill in excavation from oil tank removal at the East Parcel
  • Demo sidewalks and stairs next to Building C

Week of July 24:

  • Continue demolition of the Field House
  • Remove topsoil and environmentally impacted soil (as required) from the West Parcel
  • Start utility work outside of Building C
  • Excavate footings for the King Street Bridge at Building C

Week of July 31:

  • Continue removing soil from the West Parcel
  • Continue utility work outside of Building C
  • Begin earthwork at future Building A location for aggregate piers, and start installing piers
  • Begin earthwork at future West Parcel Parking Lot
  • Prep and pour footings for the King Street Bridge at Building C
  • Prep and pour stairs to the basement north of Building C

Week of August 7:

  • Continue utility work outside of Building C
  • Continue installing aggregate piers at future Building A location
  • Prep and pour stairs for the King Street Bridge at Building C
  • Prep sub-base for future West Parcel Parking Lot
  • Install new storm water utilities at West Parcel