The Month Ahead at Stratford High School

Week of December 18

  • Steel Erection & Decking/Detailing – West to East - Building A (New Instructional Building)

  • Pour SOD – 2nd Floor West-Third – Building A (New Instructional Building)

  • Domestic Water tie-in from curb line to Building A (New Instructional Building)

  • Run temporary power and water in Building A (New Instructional Building)

Week of December 25

  • Steel Erection & Decking/Detailing – West to East - Building A (New Instructional Building)

  • Complete Temporary Stair Tower at West End of Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 2nd Floor Center-Third - Building A (New Instructional Building)

  • Install Sanitary Manhole and west/east laterals on King Street

  • Continue temporary power and water in Building A (New Instructional Building)

  • Start Exterior Wall Mockup located in Parking Lot on east parcel

Week of January 1

  • Continue Decking/Detailing – West to East - Building A (New Instructional Building)

  • Continue Prep of Slab on Deck – 2nd Floor Center-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 2nd Floor East-Third - Building A (New Instructional Building)

  • Install Sanitary line south of Building A (New Instructional Building)

  • Continue temporary power and water in Building A (New Instructional Building)

  • Continue Exterior Wall Mockup located in Parking Lot on east parcel

Week of January 8

  • Continue Decking/Detailing – West to East - Building A (New Instructional Building)

  • Pour Slab on Deck – 2nd Floor Center-Third - Building A (New Instructional Building)

  • Continue prep of Slab on Deck – 2nd Floor East-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 3rd Floor West-Third - Building A (New Instructional Building)

  • Start Exterior CMU Walls - Building A (New Instructional Building)

  • Start Interior Layout at 1st Floor West - Building A (New Instructional Building)

  • Misc. Storm Drainage on West Parcel

Week of January 15

  • Continue Decking/Detailing – West to East - Building A (New Instructional Building)

  • Pour Slab on Deck – 2nd Floor East-Third - Building A (New Instructional Building)

  • Continue prep of Slab on Deck – 3rd Floor West-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 3rd Floor Center-Third - Building A (New Instructional Building)

  • Continue Exterior CMU Walls - Building A (New Instructional Building)

  • Start Exterior Metal Stud Walls on 1st Floor - Building A (New Instructional Building)

  • Start CMU Walls at Stair B - Building A (New Instructional Building)

  • Continue Interior Layout at 1st Floor West - Building A (New Instructional Building)

  • Misc. Storm Drainage on West Parcel

Week of January 22

  • Continue Steel Decking/Detailing – West to East - Building A (New Instructional Building)

  • Pour Slab on Deck – 3rd Floor West-Third - Building A (New Instructional Building)

  • Continue Prep of Slab on Deck – 3rd Floor Center-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 3rd Floor East-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – Roof - Building A (New Instructional Building)

  • Continue Exterior CMU Walls - Building A (New Instructional Building)

  • Continue Exterior Metal Stud Walls on 1st Floor - Building A (New Instructional Building)

  • Continue CMU Walls at Stair B - Building A (New Instructional Building)