The Month Ahead at Stratford High School

Week of October 16

  • Start Prep of Slab on Grade Building A (New Instructional Building) - West

  • Removal of Contaminated Soil at Detention System

  • Continue Under-slab Utilities at Building A (New Instructional Building) - East

  • Pour Slab on Grade – 1st Quarter – Building A (New Instructional Building) – Moving West to East

Week of October 23

  • Continue Prep of Slab on Grade Building A (New Instructional Building) – Moving West to East

  • Continue Removal of Contaminated Soil at Detention System

  • Pour Slab on Grade – 2nd Quarter – Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Install Storm Drainage North of Building A

Week of October 30

  • Continue Prep of Slab on Grade Building A (New Instructional Building) – East

  • Pour Slab on Grade – 3rd & 4th Quarter – Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Install Storm Drainage North of Building A

  • Start Low-Voltage & Electrical Ductbank along King Street

  • Prep Crane Pad

Week of November 6

  • Continue Ductbank along King Street

  • Mobilize Crane & Start Steel Erection - Building A (New Instructional Building)

  • Start Electrical Ductbank North of Building A (New Instructional Building)

Week of November 13

  • Continue Steel Erection & Decking/Detailing - Building A (New Instructional Building)

  • Continue Ductbank North of Building A (New Instructional Building)

     

Week of November 20

  • Continue Steel Erection & Decking/Detailing - Building A (New Instructional Building)

  • Continue Ductbank North of Building A (New Instructional Building)