The Month Ahead at Stratford High School - September and October

Week of September 18

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Install Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Water Tie-In at King Street

  • Test Pit at King Street for Sanitary Manhole

Week of September 25

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Backfill Footings and Under-slab at Building A (New Instructional Building)

Week of October 2

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Removal of Contaminated Soil at Detention System

  • Backfill Footings and Under-slab at Building A (New Instructional Building)

Week of October 9

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Continue Removal of Contaminated Soil at Detention System

  • Backfilling Footings, Utilities and Under-slab at Building A (New Instructional Building)

Week of October 16

  • Start Prep of Slab Subgrade Building A (New Instructional Building) - West

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Backfilling Footings, Utilities and Under-slab at Building A (New Instructional Building)

Week of October 23

  • Continue Prep of Slab Subgrade Building A (New Instructional Building) - West

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Backfilling Footings, Utilities and Under-slab at Building A (New Instructional Building)

  • Pour Slab on Grade – West End – Building A (New Instructional Building)

Road Closure Notice - King Street, September 20 and September 21.

King Street will be closed in the vicinity of the High School project on Wednesday and Thursday this week.  Thursday, September 21, is a scheduled school closure. 

 

The purpose of this work is to perform a water tap into the water main on King Street and run the new water main onto the new school parcel.

 

The other work to be performed is a Test Pit to locate utilities so a new Sanitary Manhole can be designed.

 

9/20/17

Work on 9/20 will consist of sawcutting the pavement in preparation for the excavation to take place on 9/21. This work will take place between 9 am and Noon and the road will not be closed. There will be a Police Officer on site to direct traffic around the sawcutting.

 

9/21/17

The work on 9/21 will consist of the excavation, water tap, installing pipe, backfilling and paving. Also there will be excavation and backfilling in the proposed Sanitary Manhole location. This work will start at 7 am and finish sometime between 4 pm and 7 pm.

 

King Street will be completely closed from just south of the carwash entrance to just north of the south entrance of the school parking lot.

 

There will be access for local traffic only past the intersection of King Street and Catherine Street. There will be access from Barnum Ave only for the carwash and the north side of the school.

The Month Ahead at Stratford High School - August and September 2017

Week of August 21

  • Prep Parking Lot at West Parcel (@ California Street)

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Install Storm Drainage at West Parcel

  • Restore Landscaping, Paving & Sidewalk at North and West of Existing Building C (East Parcel)

  • Form & Install Rebar for Stairs to Basement at North of Existing Building C (East Parcel)

  • Export Topsoil from 25 North Parade (Acquired Residential Property)

Week of August 28

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Pour Stairs to Basement at North of Existing Building C (East Parcel)

Week of September 4

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Start Storm Detention System at West Parcel

Week of September 11

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Continue Storm Detention System at West Parcel

  • Start Backfilling Footings at Building A

Week of September 18

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Continue Storm Detention System at West Parcel

  • Continue Backfilling Footings at Building A

  • Start Under-slab Utilities at Building A

  • King Street Water Line Tie-in for Existing Building C

Week of September 25

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Continue Backfilling Footings at Building A

  • Continue Under-slab Utilities at Building A

Road Closure Notice - July 25, 2017

Due to construction activity at Stratford High School, there will be a closure of a portion of King Street on Tuesday July 25, 2017.  This work is scheduled to be completed in one day.  The road will be closed to ALL traffic at Barnum Ave. & King Street.  There will be a road closed to Thru traffic at Broadbridge Ave. & King Street with detour signs, this will allow only residents of King Street to get home (a police officer will be posted at that location).  At the first driveway of the high school on King Street the road will be completely closed from sidewalk to sidewalk.

The Month Ahead at Stratford High School - July 18, 2017

 

Work is underway to make the new state of the art Stratford High School a reality.  See below for a summary of the activities that will be happening on the site over the next month.  All activities are subject to change due to weather conditions, etc. Regular updates will be posted here so check back frequently!

Week of July 17:

  • Remove topsoil and install Turner Construction field office on the West Parcel
  • Begin demolition of the Field House
  • Install the Turner Construction field office at 25 North Parade
  • Fill in excavation from oil tank removal at the East Parcel
  • Demo sidewalks and stairs next to Building C

Week of July 24:

  • Continue demolition of the Field House
  • Remove topsoil and environmentally impacted soil (as required) from the West Parcel
  • Start utility work outside of Building C
  • Excavate footings for the King Street Bridge at Building C

Week of July 31:

  • Continue removing soil from the West Parcel
  • Continue utility work outside of Building C
  • Begin earthwork at future Building A location for aggregate piers, and start installing piers
  • Begin earthwork at future West Parcel Parking Lot
  • Prep and pour footings for the King Street Bridge at Building C
  • Prep and pour stairs to the basement north of Building C

Week of August 7:

  • Continue utility work outside of Building C
  • Continue installing aggregate piers at future Building A location
  • Prep and pour stairs for the King Street Bridge at Building C
  • Prep sub-base for future West Parcel Parking Lot
  • Install new storm water utilities at West Parcel