Road Closure February 16 - 19th, 2018

Stratford - Due to construction activity scheduled during this weekend, King Street south of Barnum Avenue (in the area of Stratford High School) will be closed to through traffic during the day.  In order to minimize the disruption this closure is planned during a scheduled school break.  All places of Business and Residences in this area will remain accessible and open.  A closure plan has been approved by the town and will remain in effect until this construction is completed. 

This work is needed to perform utility connections to Stratford High School currently under construction.  Questions about the closure can be addressed to Public Safety Consultant Larry Ciccarelli, lciccarelli@townofstratford.com

Thank you for your patience while we bring Stratford High School into the 21st century.

  

Alert - Night Work February 1-2

Stratford - Due to construction activity scheduled for Stratford High School, utility crews will be working on King Street south of Barnum Avenue (in the area of Stratford High School) during the overnight hours beginning at approximately 10:00pm on February 1st and ending by approximately 6:00am on February 2nd (one night).  In order to minimize the disruption this work, needed to perform utility connections to Stratford High School, is required to occur while the school is not in use.  This work should have no impact on places of business and residences in this area.

The Month Ahead at Stratford High School

Week of January 15

  • Decking/Detailing - Roof - West to East - Building A (New Instructional Building)

  • Prep/Pour of Slab on Decks - 2nd Floor - West to East - Building A

  • Exterior/Stair CMU Walls - 1st Floor - West to East - Building A

  • Storm Drainage South of the Detention Basin - West Parcel

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

 

Week of January 22

  • Decking/Detailing - Roof - West to East - Building A (New Instructional Building)

  • Prep/Pour of Slab on Decks - 2nd/3rd  Floor - West to East - Building A

  • Exterior/Stair/Interior CMU Walls - 1st Floor - West to East - Building A

  • Exterior Cold Formed Metal Framed Walls/Blocking/Densglas - 1st Floor - West to East - Building A

  • Storm Drainage South of the Detention Basin - West Parcel

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

     

Week of January 29

  • Complete Decking/Detailing - Roof - Building A (New Instructional Building)

  • Prep/Pour of Slab on Decks - 3rd Floor/Roof - West to East - Building A

  • Exterior/Stair/Interior CMU Walls - 1st Floor - West to East - Building A

  • Exterior CFMF Walls/Blocking/Densglas - 1st Floor - West to East - Building A

  • Steel Pan Stairs - West Stair - Building A

  • Interior Framed Wall Layout - 1st Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Sanitary Line South Side of Building A

     

Week of February 5

  • Complete Pour of Slab on Decks - 3rd Floor/Roof - West to East - Building A (New Instructional Building)

  • Exterior/Stair/Interior CMU Walls - 1st Floor - West to East - Building A

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs - West/North Stair - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Sanitary Line South Side of Building A

     

     

Week of February 12

  • Exterior/Stair/Interior CMU Walls - 1st Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd - West to East - Building A

  • Steel Pan Stairs – North Stair - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Sanitary Lateral from King Street Manhole Stub Out to Curb Line onto East Parcel

     

Week of February 19

  • Exterior/Stair/Interior CMU Walls - 1st Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – North - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Water Tie In at King Street for Hydrant

The Month Ahead at Stratford High School

Week of December 18

  • Steel Erection & Decking/Detailing – West to East - Building A (New Instructional Building)

  • Pour SOD – 2nd Floor West-Third – Building A (New Instructional Building)

  • Domestic Water tie-in from curb line to Building A (New Instructional Building)

  • Run temporary power and water in Building A (New Instructional Building)

Week of December 25

  • Steel Erection & Decking/Detailing – West to East - Building A (New Instructional Building)

  • Complete Temporary Stair Tower at West End of Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 2nd Floor Center-Third - Building A (New Instructional Building)

  • Install Sanitary Manhole and west/east laterals on King Street

  • Continue temporary power and water in Building A (New Instructional Building)

  • Start Exterior Wall Mockup located in Parking Lot on east parcel

Week of January 1

  • Continue Decking/Detailing – West to East - Building A (New Instructional Building)

  • Continue Prep of Slab on Deck – 2nd Floor Center-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 2nd Floor East-Third - Building A (New Instructional Building)

  • Install Sanitary line south of Building A (New Instructional Building)

  • Continue temporary power and water in Building A (New Instructional Building)

  • Continue Exterior Wall Mockup located in Parking Lot on east parcel

Week of January 8

  • Continue Decking/Detailing – West to East - Building A (New Instructional Building)

  • Pour Slab on Deck – 2nd Floor Center-Third - Building A (New Instructional Building)

  • Continue prep of Slab on Deck – 2nd Floor East-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 3rd Floor West-Third - Building A (New Instructional Building)

  • Start Exterior CMU Walls - Building A (New Instructional Building)

  • Start Interior Layout at 1st Floor West - Building A (New Instructional Building)

  • Misc. Storm Drainage on West Parcel

Week of January 15

  • Continue Decking/Detailing – West to East - Building A (New Instructional Building)

  • Pour Slab on Deck – 2nd Floor East-Third - Building A (New Instructional Building)

  • Continue prep of Slab on Deck – 3rd Floor West-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 3rd Floor Center-Third - Building A (New Instructional Building)

  • Continue Exterior CMU Walls - Building A (New Instructional Building)

  • Start Exterior Metal Stud Walls on 1st Floor - Building A (New Instructional Building)

  • Start CMU Walls at Stair B - Building A (New Instructional Building)

  • Continue Interior Layout at 1st Floor West - Building A (New Instructional Building)

  • Misc. Storm Drainage on West Parcel

Week of January 22

  • Continue Steel Decking/Detailing – West to East - Building A (New Instructional Building)

  • Pour Slab on Deck – 3rd Floor West-Third - Building A (New Instructional Building)

  • Continue Prep of Slab on Deck – 3rd Floor Center-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – 3rd Floor East-Third - Building A (New Instructional Building)

  • Start Prep of Slab on Deck – Roof - Building A (New Instructional Building)

  • Continue Exterior CMU Walls - Building A (New Instructional Building)

  • Continue Exterior Metal Stud Walls on 1st Floor - Building A (New Instructional Building)

  • Continue CMU Walls at Stair B - Building A (New Instructional Building)

Road Closure Notice for Utility Work

Stratford - Due to construction activity scheduled in late December, King Street south of Barnum Avenue (in the area of Stratford High School) will be closed to through traffic during the day.  In order to minimize the disruption this closure is planned for the week of December 26 through December 29, 2017 (during a scheduled school break).  All places of Business and Residences in this area will remain accessible and open.  A closure plan has been approved by the town and will remain in effect until this construction is completed. 

This work is needed to perform utility connections to Stratford High School currently under construction.  Questions about the closure can be addressed to Public Safety Consultant Larry Ciccarelli, lciccarelli@townofstratford.com