The Month Ahead at Stratford High School

Week of October 16

  • Start Prep of Slab on Grade Building A (New Instructional Building) - West

  • Removal of Contaminated Soil at Detention System

  • Continue Under-slab Utilities at Building A (New Instructional Building) - East

  • Pour Slab on Grade – 1st Quarter – Building A (New Instructional Building) – Moving West to East

Week of October 23

  • Continue Prep of Slab on Grade Building A (New Instructional Building) – Moving West to East

  • Continue Removal of Contaminated Soil at Detention System

  • Pour Slab on Grade – 2nd Quarter – Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Install Storm Drainage North of Building A

Week of October 30

  • Continue Prep of Slab on Grade Building A (New Instructional Building) – East

  • Pour Slab on Grade – 3rd & 4th Quarter – Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Install Storm Drainage North of Building A

  • Start Low-Voltage & Electrical Ductbank along King Street

  • Prep Crane Pad

Week of November 6

  • Continue Ductbank along King Street

  • Mobilize Crane & Start Steel Erection - Building A (New Instructional Building)

  • Start Electrical Ductbank North of Building A (New Instructional Building)

Week of November 13

  • Continue Steel Erection & Decking/Detailing - Building A (New Instructional Building)

  • Continue Ductbank North of Building A (New Instructional Building)

     

Week of November 20

  • Continue Steel Erection & Decking/Detailing - Building A (New Instructional Building)

  • Continue Ductbank North of Building A (New Instructional Building)

     

The Month Ahead at Stratford High School - September and October

Week of September 18

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Install Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Water Tie-In at King Street

  • Test Pit at King Street for Sanitary Manhole

Week of September 25

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Backfill Footings and Under-slab at Building A (New Instructional Building)

Week of October 2

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Removal of Contaminated Soil at Detention System

  • Backfill Footings and Under-slab at Building A (New Instructional Building)

Week of October 9

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Continue Removal of Contaminated Soil at Detention System

  • Backfilling Footings, Utilities and Under-slab at Building A (New Instructional Building)

Week of October 16

  • Start Prep of Slab Subgrade Building A (New Instructional Building) - West

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Backfilling Footings, Utilities and Under-slab at Building A (New Instructional Building)

Week of October 23

  • Continue Prep of Slab Subgrade Building A (New Instructional Building) - West

  • Continue Storm Drainage at West Parcel

  • Under-slab Utilities at Building A (New Instructional Building)

  • Install Detention System at West Parcel

  • Backfilling Footings, Utilities and Under-slab at Building A (New Instructional Building)

  • Pour Slab on Grade – West End – Building A (New Instructional Building)

Road Closure Notice - King Street, September 20 and September 21.

King Street will be closed in the vicinity of the High School project on Wednesday and Thursday this week.  Thursday, September 21, is a scheduled school closure. 

 

The purpose of this work is to perform a water tap into the water main on King Street and run the new water main onto the new school parcel.

 

The other work to be performed is a Test Pit to locate utilities so a new Sanitary Manhole can be designed.

 

9/20/17

Work on 9/20 will consist of sawcutting the pavement in preparation for the excavation to take place on 9/21. This work will take place between 9 am and Noon and the road will not be closed. There will be a Police Officer on site to direct traffic around the sawcutting.

 

9/21/17

The work on 9/21 will consist of the excavation, water tap, installing pipe, backfilling and paving. Also there will be excavation and backfilling in the proposed Sanitary Manhole location. This work will start at 7 am and finish sometime between 4 pm and 7 pm.

 

King Street will be completely closed from just south of the carwash entrance to just north of the south entrance of the school parking lot.

 

There will be access for local traffic only past the intersection of King Street and Catherine Street. There will be access from Barnum Ave only for the carwash and the north side of the school.

The Month Ahead at Stratford High School - August and September 2017

Week of August 21

  • Prep Parking Lot at West Parcel (@ California Street)

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Install Storm Drainage at West Parcel

  • Restore Landscaping, Paving & Sidewalk at North and West of Existing Building C (East Parcel)

  • Form & Install Rebar for Stairs to Basement at North of Existing Building C (East Parcel)

  • Export Topsoil from 25 North Parade (Acquired Residential Property)

Week of August 28

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Pour Stairs to Basement at North of Existing Building C (East Parcel)

Week of September 4

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Start Storm Detention System at West Parcel

Week of September 11

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Continue Storm Detention System at West Parcel

  • Start Backfilling Footings at Building A

Week of September 18

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Continue Storm Detention System at West Parcel

  • Continue Backfilling Footings at Building A

  • Start Under-slab Utilities at Building A

  • King Street Water Line Tie-in for Existing Building C

Week of September 25

  • Excavate and Pour Footings & Foundations at Building A (New Instructional Building)

  • Continue Storm Drainage at West Parcel

  • Continue Backfilling Footings at Building A

  • Continue Under-slab Utilities at Building A

Road Closure Notice - July 25, 2017

Due to construction activity at Stratford High School, there will be a closure of a portion of King Street on Tuesday July 25, 2017.  This work is scheduled to be completed in one day.  The road will be closed to ALL traffic at Barnum Ave. & King Street.  There will be a road closed to Thru traffic at Broadbridge Ave. & King Street with detour signs, this will allow only residents of King Street to get home (a police officer will be posted at that location).  At the first driveway of the high school on King Street the road will be completely closed from sidewalk to sidewalk.