Six Week Look ahead May 7, 2018

Week of May 7

·         Exterior Vapor Barrier and Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Build out of new Electric Room – Building A

·         Grounding and Transformer Pad for New Electric Service to Building A

·         Overhead & In Wall MEP, begin regular AHJ In Wall Inspections – All Floors -  West to East - Building A

·         Gypsum Board and Taping at 1st and 3rd Floors

·         Roof and Metal Panel for Bridge Pre-Assembly

·         Waterproof & Backfill for Building C Elevator Foundation

·         Pour concrete infills for Stair A – Building A

·         Start Steel Framing for Stair D – Building A

Week of May 14

·         Exterior Vapor Barrier and Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Start Windows – West to East – Building A

·         Build out of new Electric Room – Building A

·         UI – Pull Wire from Pole in Street to new Transformer for New Electric Service to Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – All Floors -  West to East - Building A

·         Gypsum Board and Taping at 1st and 3rd Floors

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Continue Steel Framing for Stair D – Building A

·         Rig Roof Top Equipment to Roof – Building A

·         Piping and Duct on Roof – Building A

·         Low Roof Over Cafeteria – Building A

Week of May 21

·         Exterior Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Windows – West to East – Building A

·         Start Metal Panel at East End – Building A

·         Complete AHJ In Wall Inspection – 3rd Floor East

·         Build out of new Electric Room – Secondary from Transformer to Switchgear – Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – 2nd Floor – West to East - Building A

·         Gypsum Board and Taping at 1st and 3rd Floors

·         Build out Mechanical Rooms on 1st Floor – Building A

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Complete Steel Framing for Stair D & Pour Concrete – Building A

·         Piping and Duct on Roof – Building A

·         Prime and 1st Coat Paint on 3rd Floor West – Building A

Week of May 28

·         Exterior Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Windows – West to East – Building A

·         Metal Panel at East End – Building A

·         Build out of new Electric Room – Secondary from Transformer to Switchgear – Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – 2nd Floor –  West to East - Building A

·         Gypsum Board and Taping at 1st and 3rd Floors

·         Build out Mechanical Rooms on 1st Floor – Building A

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Piping and Duct on Roof – Building A

·         Prime and 1st Coat Paint on 1st Floor East – Building A

·         Pull Low Voltage Wiring on 3rd Floor West

Week of June 4

·         Exterior Brick - West to East - Building A (New Instructional Building)

·         Interior CMU at Bathrooms and MEP Chases – Building A

·         Windows – West to East – Building A

·         Metal Panel at East End – Building A

·         Build out of new Electric Room – Secondary from Transformer to Switchgear – Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – 2nd Floor -  West to East - Building A

·         Gypsum Board and Taping at 1st , 2nd  and 3rd Floors

·         Build out Mechanical Rooms on 1st Floor – Building A

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Piping and Duct on Roof – Building A

·         Prime and 1st Coat Paint on 1st Floor West – Building A

·         Pull Low Voltage Wiring on 1st Floor East – Building A

·         Start Ceiling Grid on 3rd Floor West – Building A

·         Start Kitchen Ceilings – Building A

Week of June 11

·         Windows – West to East – Building A

·         Start up Permanent Power – Building A

·         Start Up Roof Top Equipment – Building A

·         Overhead & In Wall MEP, continue regular AHJ In Wall Inspections – 2nd Floor -  West to East - Building A

·         Gypsum Board and Taping at 1st, 2nd and 3rd Floors

·         Build out Mechanical Rooms on 1st Floor – Building A

·         Metal Panel for Bridge Pre-Assembly

·         CMU for Building C Elevator Shaft

·         Install Piping and Duct on Roof – Building A

·         Prime and 1st Coat Paint on 3rd Floor East – Building A

·         Pull Low Voltage Wiring on 1st Floor East – Building A

·         Start Ceiling Grid on 1st Floor East and continue on 3rd Floor west – Building A

·         Kitchen Ceilings – Building A

April 2018 - East Parcel Work Commencing Soon

To: Stratford High School Neighbors

From: Larry Ciccarelli, Stratford Public Safety Consultant

Subject: Stratford High School Construction Activities

Date: April 6, 2018

 

As you are likely already aware, the Town of Stratford is in the midst of a substantial construction project to remake the existing Stratford High School.  As we approach the summer 2018 construction crunch period, I wanted to reach out to you to alert you that significant activity is planned for the East parcel (where the current School is located, between King Street and North Parade Street).  Some utility work is scheduled to occur on the East parcel during the April school recess, from April 6-15.  Until now most of the activity has been focused on the West parcel (between California Street and King Street). 

 

As a result of this anticipated activity on the East parcel, you may notice surveyor’s stakes, or painted markings identifying property lines and underground utilities.  You may also notice construction workers working along the fence line that separates the school from your property, this should be expected because the fence is scheduled to be replaced.  If you have personal property or cherished plantings that may become damaged during the work along the fence line, I encourage you to move those items very soon to a safer location.

 

For more information visit the project website and to sign-up for updates.  In signing-up for notices, if there are any planned road closures that may impact you, you should receive an email notification in advance.  www.stratfordhighproject.com

 

If you have any concerns as we move through this important project for the Town of Stratford, I offer the following contact information (or contact me, my information is on this notice):

Tim Klepps, Project Manager, Turner Construction, 203-627-6028, tklepps@tcco.com

Richard Snedeker, Project Manager, CREC Construction Services, 860-550-1336, rsnedeker@crec.org

John Casey, Stratford Town Engineer, 203-385-4013, jcasey@townofstratford.com

 

As always, if you witness activity or people on your property that you are not comfortable with, or if you are unsure, call 911.

 

Thank you in advance for your patience and understanding while bring Stratford High School up to date for many future generations of Stratford residents

Six Week Look Ahead March 19, 2018

Stratford High School Renovations and Additions

Summary 6-Week Look Ahead As of March 19, 2018

 

Week of March 19

·         Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

·         Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Roofing for Temp. Watertight – West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st Floor -  West to East - Building A

·         Bathroom Carriers – 1st Floor

·         Isolation Ceiling in Kitchen – Building A

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Delivery of Bridge for Prefab

Week of March 26

·         Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

·         Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Complete Roofing for Temp. Watertight – West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead MEP – 1st Floor/3rd Floor-  West to East - Building A

·         In Wall MEP Rough - 1st/2nd/3rd Floors -  West to East - Building A

·         Bathroom Carriers – 1st Floor/3rd Floor

·         Isolation Ceiling in Kitchen – Building A

·         Start AVB - 1st/2nd/3rd Floor - West to East - Building A

·         Fireproofing – 1st Floor – Building A

·         Rig Rooftop Equipment to Roof – Building A

·         Excavate for Elevator Pit – Building C

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Decking/Framing/Roofing

Week of April 2

·         Stair/Interior CMU Walls - 1st/2nd/3rd Floor - West to East - Building A (New Instructional Building)

·         Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st/2nd/3rd Floors -  West to East - Building A

·         Bathroom Carriers – 3rd Floor/2nd Floor

·         Isolation Ceiling in Kitchen – Building A

·         AVB - 1st/2nd/3rd Floor - West to East - Building A

·         Rig Rooftop Equipment to Roof – Building A

·         Install Rooftop MEP – Building A

·         Install Foundations for Elevator Pit – Building C

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Framing

Week of April 9

·         Stair/Interior CMU Walls – 1st/2nd/3rd Floor - West to East - Building A (New Instructional Building)

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st/2nd/3rd Floors -  West to East - Building A

·         AVB - 1st/2nd/3rd Floor - West to East - Building A

·         Install Rooftop MEP – Building A

·         CMU Walls for Elevator – Building C

·         Brick/Precast Installation - 1st/2nd/3rd Floor - West to East - Building A

·         Steel Pan Stairs – North/East - Building A

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Insulation/Sheathing/AVB/Metal Panel

·         Misc. Prep Work in Building C (Spring Break)

·         Run Sanitary Line on East Parcel (Spring Break)

Week of April 16

·         Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st/2nd/3rd Floors -  West to East - Building A

·         AVB - 1st/2nd/3rd Floor - West to East - Building A

·         CMU Walls for Elevator – Building C

·         Brick/Precast Installation - 1st/2nd/3rd Floor - West to East - Building A

·         Steel Pan Stairs – North/East - Building A

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Metal Panel

Week of April 23

·         Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

·         Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

·         Build out of new Electric Room – Building A

·         Overhead & In Wall MEP – 1st/2nd/3rd Floors -  West to East - Building A

·         AVB - 1st/2nd/3rd Floor - West to East - Building A

·         CMU Walls for Elevator – Building C

·         Brick/Precast Installation - 1st/2nd/3rd Floor - West to East - Building A

·         Steel Pan Stairs – North/East - Building A

·         Start Metal Panel – West Elevation – Building A

·         Exterior Wall Mockup located in School Parking Lot on East Parcel

·         Prefab of Bridge – Metal Panel

The Month Ahead at Stratford High School

I've you've been in the neighborhood over the past few months, you probably noticed the new building rising next to the High School.  The brand new, state of the art instructional building continues to be built at a rapid pace.  This is what is happening now, and planned for the next month, as the Project Team continues to bring Stratford High School into the 21st century.

Week of February 19

  • Exterior/Stair/Interior CMU Walls - 1st Floor/2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – West - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Water Tie In at King Street for Hydrant

  • Electric Room Infrastructure & Rough-in – Building A

  • Install new Gas Service from California Street for Building A

 

Week of February 26

  • Stair/Interior CMU Walls - 1st Floor/2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – West/North - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Water pipe from King Street curb line for Hydrant

  • Electric Room Infrastructure & Rough-in – Building A

  • Test Pit for Building C Elevator Foundations – East Parcel

  • Install new Gas Service from California Street for Building A

     

Week of March 5

  • Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – North - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Electric Room Infrastructure & Rough-in – Building A

  • Deliver Bridge Structure

 

 

Week of March 12

  • Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – North/East - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Electric Room Infrastructure & Rough-in – Building A

  • Prefab of Bridge – Decking/Framing/Roofing/Metal Panel

  • Start Ductwork – 1st/3rd Floors - West to East - Building A

     

     

Week of March 19

  • Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – North/East - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Roofing – West to East - Building A

  • Electric Room Infrastructure & Rough-in – Building A

  • Prefab of Bridge – Decking/Framing/Roofing/Metal Panel

  • Install Ductwork – 1st/3rd Floors - West to East - Building A

  • Start Overhead MEP – 1st/3rd Floors -  West to East - Building A

     

     

Week of March 26

  • Start Exterior Wall AVB

  • Stair/Interior CMU Walls - 2nd Floor/3rd Floor - West to East - Building A (New Instructional Building)

  • Exterior CFMF Walls/Blocking/Densglas - 1st/2nd/3rd Floor - West to East - Building A

  • Steel Pan Stairs – East/South - Building A

  • Interior Framed Wall Layout/Framing/HM Frames - 1st/2nd/3rd Floor - West to East - Building A

  • Exterior Wall Mockup located in School Parking Lot on East Parcel

  • Complete Roofing – West to East - Building A

  • Electric Room Infrastructure & Rough-in – Building A

  • Prefab of Bridge – Decking/Framing/Roofing/Metal Panel

  • Install Ductwork – 1st/3rd Floors - West to East - Building A

  • Overhead MEP – 1st/3rd Floors -  West to East - Building A

Road Closure February 16 - 19th, 2018

Stratford - Due to construction activity scheduled during this weekend, King Street south of Barnum Avenue (in the area of Stratford High School) will be closed to through traffic during the day.  In order to minimize the disruption this closure is planned during a scheduled school break.  All places of Business and Residences in this area will remain accessible and open.  A closure plan has been approved by the town and will remain in effect until this construction is completed. 

This work is needed to perform utility connections to Stratford High School currently under construction.  Questions about the closure can be addressed to Public Safety Consultant Larry Ciccarelli, lciccarelli@townofstratford.com

Thank you for your patience while we bring Stratford High School into the 21st century.